New airport in 2035 or 2037? Government tries to anticipate openness
According to the document, the lower limit represents a reduction of more than 10% compared to the AECOM estimate and is below 8.5 billion calculated in the report..
- Center2
- Center-right1
2 agency rewrites / co-publications detected
Summary
According to the document, the lower limit represents a reduction of more than 10% compared to the AECOM estimate and is below 8.5 billion calculated in the original report. The estimate now advanced "tries to confirm the duration presented in the initial report", delivered in December 2024, assuming that agreements relating to the new airport are signed in April 2029. The budget should be updated again in January 2027 when the concessionaire submits the financial report.
Furthermore, Between 2031 and 2035 work on runways, terminals, operating buildings and technical networks should be carried out simultaneously, following the integration of systems, tests, commissioning and certification of infrastructure between 2035 and 2037. Operational preparation, known as the English acronym ORAT, can only begin at the end of 2036 and is dependent on completion of road and rail access, permanent supply networks and installations under the responsibility of other entities. The value of 8.9 billion corresponds to the reference estimate prepared by the consultant AECOM, while the 7.9 billion represent the reduction target that ANA intends to achieve by reviewing technical solutions and cost optimization measures.
Cross-referenced from 3 sources.
Factual coreconfirmed by several independent voices
According to the document, the lower limit represents a reduction of more than 10% compared to the AECOM estimate and is below 8.5 billion calculated in the original report.
reliability low1/3 sourcesThe estimate now advanced "tries to confirm the duration presented in the initial report", delivered in December 2024, assuming that agreements relating to the new airport are signed in April 2029.
reliability low1/3 sourcesThe budget should be updated again in January 2027 when the concessionaire submits the financial report.
reliability low1/3 sourcesBetween 2031 and 2035 work on runways, terminals, operating buildings and technical networks should be carried out simultaneously, following the integration of systems, tests, commissioning and certification of infrastructure between 2035 and 2037.
reliability low1/3 sourcesOperational preparation, known as the English acronym ORAT, can only begin at the end of 2036 and is dependent on completion of road and rail access, permanent supply networks and installations under the responsibility of other entities.
reliability low1/3 sourcesThe value of 8.9 billion corresponds to the reference estimate prepared by the consultant AECOM, while the 7.9 billion represent the reduction target that ANA intends to achieve by reviewing technical solutions and cost optimization measures.
reliability low1/3 sources
Disputedincompatible versions — to verify
No factual contradiction detected between sources.
Framing by sidesame fact, different words — loaded terms highlighted
No notable framing divergence.
Blind spotwhat one side keeps silent
No blind spot detected: every side covers the same facts.
Sources3 sources cross-checked
Center-right1